Home

Wesley House

Project Photos

Juried Art Exhibition

Tents of Hope

Staff

About Us

Donate

Wesley House and Campus Center
Under Construction

November 9, 2009

Preparation for pouring the footings.

November 8, 2009

The Wesley Board toured the site.

November 4 and 5, 2009

Trenches are being dug and rebar installed for the contrete footings.

October 12, 2009

Cement was poured for the retaining wall and elevator.

October 2, 2009

Concrete footings for the retaining wall and elevator pit are being poured.

September 24, 2009

More elevator pit work.

September 21, 2009

The contractors dug the elevator pit.

September 9, 2009

Plumbing is being covered and compacted.

September 3, 2009

Underground plumbing is being installed.

August 25, 2009

The soil is being compacted and graded.

August 16, 2009

August 12, 2009

The site is being prepared for construction.

August 6, 2009

The site has been cleared of debris.

August 4, 2009

The building is down. Debris is being removed today.

August 3, 2009

Demolition began this morning.

July 31, 2009

The pedestrian walkway was completed on July 27, 2009. Demolition of the old Wesley building is scheduled for Monday, August 3, 2009.