Wesley House and Campus Center
Under Construction
November 9, 2009
Preparation for pouring the footings.


November 8, 2009
The Wesley Board toured the site.
November 4 and 5, 2009
Trenches are being dug and rebar installed for the contrete footings.


October 12, 2009
Cement was poured for the retaining wall and elevator.

October 2, 2009
Concrete footings for the retaining wall and elevator pit are being poured.



September 24, 2009
More elevator pit work.
September 21, 2009
The contractors dug the elevator pit.
September 9, 2009
Plumbing is being covered and compacted.

September 3, 2009
Underground plumbing is being installed.
August 25, 2009
The soil is being compacted and graded.


August 16, 2009

August 12, 2009
The site is being prepared for construction.

August 6, 2009
The site has been cleared of debris.
August 4, 2009
The building is down. Debris is being removed today.

August 3, 2009
Demolition began this morning.





July 31, 2009
The pedestrian walkway was completed on July 27, 2009. Demolition of the old Wesley building is scheduled for Monday, August 3, 2009.