HANDICAP ACCESSIBILITY
Goals
Front door accessibility to the sanctuary level for motorized wheel chairs (MWC)
Accessibility to all levels of the church facility for MWC
Sufficient parking on near level grade at the closest practical proximity to the main handicap entrance to accommodate loading/unloading of MWC
Options
(1) Redesign main entrance to provide grade level access and elevator to all levels
(2) Redesign main entrance to provide grade level access and relocate and/or widen stairways to all levels to accommodate lift platforms for MWC
(3) Exterior ramp to main entrance and elevator to all levels
(4) Exterior ramp to main entrance and relocate and/or widen stairways to all levels to accommodate lift platforms for MWC
BUILDING EXTERIOR AND GROUNDS
Parking
Reconfigure spaces and re-grade to provide near level handicap spaces at the closest practical proximity to the main handicap entrance
Remove oak tree from parking area at end of playground and level area
Correct storm water runoff issues from parking area into playground
Pave and stripe gravel area and re-pave and stripe all currently paved areas including driveway
Leaks
Permanently fix all water infiltration issues particularly those coming from the bell tower, window wells, foundation cracks, gutter down spouts
Tower
Clean, paint, and resolve water infiltration issues
Replace and/or relocate tower lighting with fixtures that are longer lasting and more easily accessed
Paint
Clad all soffits, facia, and exterior ceilings with vinyl or aluminum
Paint all windows, doors, and other exterior wooden surfaces
Landscaping
Develop a low-maintenance landscaping plan
Upgrade fencing for rear playground area (day care funded)
SANCTUARY
Goals
To improve the versatility of the chancel area to accommodate a greater variety of worship formats
To improve the effectiveness and efficiency of audio-visual systems as worship aids
To accommodate MWC in the seating plan and chancel area
Floor Plan
Extend the chancel area forward to accommodate larger musical groups, skits, and special services such as baptism and confirmation (this may require the removal of as much as the first three rows of pews)
Remove the choir pews on the left side of the chancel to create an area for the grand piano and other musicians and instruments
Reconfigure choir area to create forward-facing seating
Handicap Access and Seating
Shorten at least two pews to allow floor space for MWC
Portable ramp for access to chancel area for MWC
Audio-Visual System
Ceiling or wall mounted retractable projection screens or flat panel monitors for congregation and choir
Control booth in the rear of the sanctuary (possibly opening from second floor) for all AV equipment
ADMINISTRATIVE OFFICES
Goals
Provide main entrance access to the Church Secretarys Office
Provide dedicated office space to church staff including Children & Youth Coordinator and summer intern
Options
Relocate secretarys office to Ladies Parlor and possibly convert the Gudger Cabe classroom to a parlor
FAMILY LIFE CENTER
Improve Acoustics
Install sound deadening acoustical panels on walls
Dedicated sound system with protected speakers
Kitchen
New stoves or one large commercial grade range and oven with vented hood
New sink faucet with removable spray head, ice maker, garbage disposal
General
Replace broken floor tiles
Install privacy walls for urinals in mens restrooms
Folding round tables on rollers (if adequate storage can be arranged)
Re-grade and install exterior door into classroom next to equipment room in day care wing so it can be added to leased space
Construct storage rooms on levels one and two of the exterior stairwell at the south end of the Family Life Center
EDUCATION BUILDING AND SOCIAL HALL
HVAC
New heating and air conditioning system
New energy efficient windows
Floor Covering
New carpet (especially on third floor)
Floor Plan
See attached floor plans with comments
A second option is to retain the kitchen and a dining/meeting area on the north side of the social hall and construct only three classrooms along the south side
STANDING COMMITTEES
Parsonage Committee
See attached report
Day Care Facility
See attached report
Cemetery Committee
Level sunken graves and reset unstable head stones
Supplement the Cemetery Endowment Fund so that yearly interest will fully cover mowing costs
GENERAL
Sewer
Connect to Metropolitan Sewerage District line when available
Out Building
Construct building with restrooms and dedicated storage at southeast end of parking lot for use as Youth classroom and Scout meeting hall