BUILDING COMMITTEE MILESTONE WORKPLAN 2007
     
General 0 DESCRIPTION Target Date Status/Update
TASK      
0.01 Prioritize Commissioned Assignment - 3 Areas (Fellowship Hall, Courtyard Evangel Center) 1/1/2007 Completed
       
0.02 Identify Renovation/Expansion Requirements for each project area - in general 3/15/2007 FH - Completed 2/28/07
      Other Areas in Process
       
0.03 Identify Process and Firm-type 02/28/07 Completed
       
0.04 Select Firms for Interview 3/15/2007 In Process
       
0.05 Develop Interview Tool and Process 3/15/2007 Draft under Committee Review
       
0.06 Letters to Prospective Firms  3/19/2007 Letters Sent
       
0.07 Schedule and Conduct Interviews 4/15/2007 Committee scheduling
       
0.08 Select Firm 5/1/2007  
       
0.09 Review General Program Plan for Projects (Submission by Firm) 7/15/2007  
       
0.10 Present General Program Plan of Projects to Congregation or Conference 7/30/2007  
       
PROJECT 1 ACT 29:2006-1.1    
TASK DESCRIPTION Target Date Status/Update
1.01 Elicit Congregational Input/Feedback/Approval - Project 1 (Fellowship Hall and Kitchen) 8/15/2007 Step to be repeated as necessary
       
1.02 Finalize Renovation of Project 1 (FH) 9/15/2007  
       
1.03 Approve and Schedule Work for Project 1 9/30/2007  
       
1.04 Approve completion of work TBD  
       
PROJECT 2 ACT 29:2006-1.3    
TASK DESCRIPTION Target Date Status/Update
2.01 Elicit Congregational Input/Feedback/Approval - Project 2 (Courtyard/Atrium) 9/15/2007 Step to be repeated as necessary
       
2.02 Finalize Renovation and Expansion of Project 2 (CA) 1/15/2008  
       
2.03 Approve and Schedule Work Project 2 4/30/2008  
       
2.04 Approve completion of work TBD  
       
PROJECT 3 ACT 29:2006-1.2    
TASK DESCRIPTION Target Date Status/Update
3.01 Elicit Congregational Input/Feedback/Approval - Project 3 (Evangel Center) 8/15/2008 Step to be repeated as necessary
       
3.02 Finalize Renovation of Project 3 (EC) 10/15/2008  
       
3.03 Finalize Expansion (including demolition as needed) for Project 3 11/15/2008  
       
3.04 Approve and Schedule Work Project 3 11/30/2008  
       
3.05 Approve completion of Work TBD