ARCHITECTURAL ISSUES AND SYSTEMS

EXTERIOR


Priority  Item                                          Cost                            Comments

High      Parapet coping repairs - caulk and seal $500

Low      Replace bell tower roof " $2,000 "

High      Tuckpoint upper brick areas at Temple House " $3,500 "

High      Replace deteriorated brick at Temple House flue stacks $300

Low      Clean black film from stone " $50,000 "

High      Refinish exterior wood doors " $1,400 "

Medium Strip. repaint and caulk windows " $40,000 "

Low      "Provide new windows to match existing in lieu of stripping, painting and caulking" " $200,000 " "Alternate cost to stripping, repainting and caulking windows "

Medium Paint exterior trim - louvers and miscellaneous trim " $4,000 "

Medium Replace and rebuild church gable end louvers " $2,500 "

Low      Provide lightning protection system " $40,000 "

                               ARCHITECTURAL ISSUES AND SYSTEMS

                                                   INTERIOR

Priority Item                                        Cost                               Comments

Medium General painting allowance for rooms not identified in individual room evaluations. " $30,000 "

Budget $0.50/sf to paint selected rooms or areas

Medium General allowance for refinishing woodwork and trim beyond areas identified in individual room evaluations  " $5,000 "

Medium New barrier free toilet on first floor " $6,000 "

Medium New barrier free toilet on second floor " $6,500 "

Low      Replace doorknob hardware with lever handles " $50,000 "

Low      Fire rate stair enclosures - including wall erection and door replacement " $75,000 "

Low      Install elevator in Temple House for gymnasium barrier free access " $100,000 "

Medium Pew modifications in Sanctuary for barrier free seating " $5,000 "

Medium Pew modifications in Chapel for barrier free seating " $1,000 "

Clean terrazzo floor Maintenance item

Medium Tile infill at terrazzo floor insets " $8,000 "